IDA have been appointed to undertake Project Management and Commissioning Management duties for this specialist main switchgear and UPS upgrade project. Our scope includes:

  • Coordinate with the Main Contractor and MEP Designer to set up the suitable and feasible Quality Assurance and T&C plan, including Method Statements, FAT and SAT
  • Review, comment and approve the proposed QA and T&C plan as an independent third-party consultant
  • Ensure the MEP systems and test results comply with the statutory requirements
  • Review the warranties terms of MEP system
  • Attend FAT and SAT
  • Chair T&C Coordination Meeting and prepare meeting notes for each meeting
  • Join the FM handover process and assist PM during handover stage
  • Provide report on the inspected and tested MEP system involved in the project and professional advice on the following up actions during DLP
  • Review, comment and approve the O&M manuals and the Practical Completion Certification prior to issuance

 

LOCATION

Asia, Hong Kong

SECTOR

Commercial Interiors

CLIENT

HSBC

BUILDING AREA

Confidential

IT LOAD

N/A

SERVICE TYPE

Commissioning Management, Specialist Consultancy

COMPLETION

2021